RSS

The operation progress of many power plant projects in PDP is still unclear

08:35 |26/11/2020

According to the reliable update information, there are 13 power plants in Power Development Planning VII (adjusted) with a total capacity of 17,040 MW could not be put into operation in the 2026 – 2030 ...

The first fire for the boiler of Unit 2 of Song Hau 1 thermal power project

08:10 |06/11/2020

On November 5, 2020, Vietnam National Oil and Gas Group (PVN), Song Hau 1 Petroleum Power Project Management Board (Investor), and the General Contractor - Vietnam Machinery Erection Corporation (Lilama) successfully set on the first ...

The proposal to converse Vung Ang power center 3 from coal to LNG burning in PDP VIII

07:45 |04/11/2020

Ha Tinh Provincial People's Committee (PPC) has just issued a document to the Ministry of Industry and Trade (MOIT) with a proposal to converse in Power Development Planning VIII (PDPVIII) Vung Ang power center 3 ...

Updating progress of 10 key power plant projects in Vietnam

12:58 |29/10/2020

The Vietnam Energy Magazine's progress update report on key power projects shows that, although there are still difficulties, but almost projects are going on schedule. The latest information on projects at Quang Trach Power Center, ...

Signing a MOU for Quang Ninh LNG Power Project

14:16 |22/10/2020

On October 19, 2020, in the presence of Vietnamese Prime Minister Nguyen Xuan Phuc and Japanese Prime Minister Suga Yoshihide, the consortium of investors including PetroVietnam Power Corporation (PV Power), Vietnam Mechanical and Machine Assembly ...

A proposal to include 2 LNG power projects in Hai Phong in the PDP VIII

06:39 |05/10/2020

The Standing Committee of Hai Phong City Party Committee has agreed with the investment policy and proposal to include two LNG Gas Turbine Combined Cycle (GTCC) with a total capacity of 6,100 MW in Tien ...

Successfully energizing the first 500kV power grid projects invested by private sector in Vietnam

10:40 |04/10/2020

On September 29, 2020, in Quan The Hamlet, Phuoc Minh Commune, Thuan Nam District, Ninh Thuan Province, Trung Nam Investment and Construction Joint Stock Company (Trungnam Group) successfully energizing the first super high voltage project ...

The Value of a Real End-to-End Lateral-Protection Strategy

08:32 |02/10/2020

The COVID-19 pandemic has resulted in a significant increase in demand for reliable power at the grid’s edge, making lateral-protection strategies more important than ever. With a shift to more “at-home” lifestyles becoming the norm, ...

EVN has effectively used capital from global financial institutions

05:49 |28/09/2020

On September 22, 2020, in Hanoi, Mr. Tran Dinh Nhan - General Director of Electricity of Vietnam (EVN) had a working meeting with Mr. Andrew Jeffries – ADB Country Director for Vietnam. Discussing with EVN ...

Powering 500 kV Chon Thanh Transformer Substation Project

11:18 |04/09/2020

At 6:55 am on September 2, 2020, at 500 kV Chon Thanh Transformer Substation, the Central Power Project Management Board (CPMB) in cooperation with other organizations powered and put 500 kV Chon Thanh transformer substation ...

The First Workshop on National Energy Master Plan

07:03 |01/09/2020

On August 28, 2020, in Hanoi, Ministry of Industry and Trade (MOIT) held the first workshop on the National Energy Master Plan (NEMP) for 2021-2030 period, with a vision up to 2050.

"The bottleneck" of the ground for Nhon Trach 3 and 4 power projects has been removed

12:53 |25/08/2020

At the meeting with PetroVietnam Power Corporation (PV Power) and Tin Nghia Corporation on cleaning the plan ground for Nhon Trach 3 and 4 power projects, Chairman of Dong Nai Provincial People's Committee (PPC) agreed ...

The information about BOT power projects

10:19 |04/08/2020

At the present, the situations on implementing Vung Ang 2, Nam Dinh 1, Vinh Tan 3 and Song Hau 2 Build – Operate –Transfer (BOT) projects will be officially signed in the third ...

Powering the project for increasing transmission capacity of 220 kV Cu Chi – Trang Bang line

08:36 |21/07/2020

At 19h06 on July 19, 2020, at 220 kV Trang Bang transformer substation, the Southern Power Project Management Board (SPMB) and relevant units organized to power and put into operation the project for increasing ...

Signing EPC contract for coal port and jetty of Quang Trach Power Center project

08:33 |14/07/2020

On July 11, 2020 in Quang Binh, Power Project Management Unit 2 (PMU 2), and Consortium of Phu Xuan Consulting and Construction Joint Stock Company, Pacific Group Joint Stock Company and Hydraulic Engineering Construction Joint ...

There will be 'one-price tariff' for electricity customers to choose

09:01 |10/07/2020

Sharing with the press on July 8, Deputy Minister of Industry and Trade Hoang Quoc Vuong informed: Besides the electricity tariff with 5 price ladders instead of the current tariff with 6 ladders, ...

Đầu << 15 trước - 1 2 3 4 5 - Tiếp 15 >> Cuối