Prospect of Russian technology in Vietnam's energy projects

10:45 |29/11/2017

The cooperation between Power Machines – PM (Russia) and Energy sector of Vietnam has been started for more than half a century by providing generators for Thac Ba hydropower plant, and then for Uong Bi, ...

The unit No2 of Vinh Tan 4 TPP has been successfully synchronized

08:24 |04/10/2017

According to the information from Electricity of Vietnam (EVN), at 10:25 on Oct. 3, 2017, the unit No2 of Vinh Tan 4 Thermal Power Plant (TPP) has been successfully synchronized with the National Power System. ...

Power Machines with a new vision into the electricity market of Vietnam

14:05 |16/08/2017

Cooperation relationship between Power Machines (Russian Federation) and Vietnam began more than a half century ago with the delivery of three generators for Thac Ba hydraulic power plant, which was the country's most powerful one ...

Vinacomin has successfully applied CFB technology in the thermal power plants

09:29 |19/07/2017

According to the information from Vietnam National Coal – Mineral Industries Holding Corporation Limited (Vinacomin), after surveying worldwide experience for circulating fluidized bet (CFB) boiler technology, a technology for bad coal (low calorific value and ...

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

08:40 |29/06/2017

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is ...

Unit#1 of Thai Binh 1 Thermal Power Plant has synchronized with the National Power System

09:28 |25/05/2017

At 18.00 on 23 May 2017, Unit#1 of Thai Binh1 Thermal Power Plant (TPP) has successfully connected to the National Power System.

Vietnam has successfully made an air dryer for the boiler in coal-fired thermal power plant

09:40 |11/05/2017

Specialists from the National Research Institute for Mechanical Engineering - NARIME (Ministry of Industry and Trade) have successfully researched, designed and made a rotary heat recovery air dryer for boiler in coal-fired thermal power plant.

Unit 2 of Duyen Hai 3 TPP has been officially put into commercial operation

10:48 |20/04/2017

Duyen Hai Thermal Power Company has officially received Unit 2 of Duyen Hai 3 Thermal Power Plant (TPP) from the Thermal Power Project 3 Management Board, Consultants Contractors.

Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

08:15 |21/12/2016

The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.

Three power projects of EVN have to be urgently developed

08:18 |19/12/2016

These three projects as Quang Trach Power Center (including thermal power plants Quang Trach 1 (2x600 MW),Quang Trach 2 (2x600 MW) and Quang Trach Coal Harbor), Bac Ai Hydropower Pump Storage Plant (4x300 MW) and ...

Signing the credit and commercial loan contracts for Song Hau 1 Thermal Power Project

09:18 |25/11/2016

According to information from PVN, on November 23, 2016 there was taken place the ceremony of signing credit contract and commercial loan contract with total value of USD 1.2 billion, between PVN and Korea Export-Import ...

PVN signed the principle contract to supply imported coal for PV Power thermal power plants

19:53 |06/11/2016

On November 2, 2016 in Hanoi, the Vietnam Oil and Gas Group (VN) in collaboration with the PetroVietnam Power Corporation (PV Power) held a cerymony to sign the principle contract to supply imported coal for ...

Projects to be implemented at two thermal power plants in northern Vietnam

16:38 |25/10/2016

Prime Minister Nguyen Xuan Phuc has issued instructions on the projects at the An Khanh–Bac Giang Thermal Power Plant in the northern province of Bac Giang and Duc Giang–Lao Cai Thermal Power Plant in the ...

Power Purchasing Contract signing for Vung Ang TPP No1

09:50 |23/08/2016

On August 17, 2016 in Hanoi, PetroVietnam (PVN), Electricity of Vietnam (EVN), PV Power and EVN Electricity Power Trading Company held a ceremony to sign the Power Purchase Contract (PPC) for Vung Ang ...

Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant

17:23 |16/08/2016

At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure ...