The unit No2 of Vinh Tan 4 TPP has been successfully synchronized

08:24 |04/10/2017

According to the information from Electricity of Vietnam (EVN), at 10:25 on Oct. 3, 2017, the unit No2 of Vinh Tan 4 Thermal Power Plant (TPP) has been successfully synchronized with the National Power System. ...

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

08:40 |29/06/2017

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is ...

The Unit No2 of Xekaman Hydropower plant No1 has synchronized with National Power System

16:32 |05/12/2016

Information from the Central Power Corporation (EVNCPC) said, on November 29, 2016, the Unit No2 of Xekaman Hydropower plant (HPP) No1 has successfully synchronized with national power system.

Unit No. 2 of Vung Ang 1 Thermal Power Plant has been officially put into commercial operation

23:15 |14/05/2015

On May 12, Limama EPC general contractor handed over the Unit No. 2 of Vung Ang 1 Thermal Power Plant (TPP) to the Petroietnam (PVN) investor for commercial operation.

Unit No 1 of Song Bung 4 HP has been synchronized with the National Power System

09:39 |06/10/2014

The Electricity of Vietnam (EVN) informed, unit No1 of the Song Bung 4 Hydropower Plant (HP) has been synchronized with the National Power System through Thanh My 500/220kV transformer substation.