Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

08:15 |21/12/2016

The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.

Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant

17:23 |16/08/2016

At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure ...

Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant

08:53 |27/07/2016

Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.

Signing the contract for the ash and slag discharging system of Thai Binh 2 Thermal Power Plant

10:46 |05/06/2015

PetroVietnam Construction Joint Stock Company (PVC) and the consortium of bidders - PVC-PT / MIE / Viettronics have signed a contract for design, materials and equipment supply, installation and test operation of the ash and ...

Thai Binh 2 Thermal Power Plant has been made the Cooling Pipe System by Vietnam

09:16 |27/05/2015

Petroleum Pipeline and Tank Construction Joint Stock Company (PVC-PT) has held a starting ceremony for the bidding package "Manufacture and installation of cooling water supplying and draining pipeline system " for Thai Binh 2 Thermal ...