RSS

Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

08:15 |21/12/2016

The Vietnam Lilama Corporation has successfully implemented high pressure test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and control of the experts from PetroVietnam.

Successful pressure tests for boiler 1 and low pressure package of boiler 2 in Thai Binh 2 thermal power plant

17:23 |16/08/2016

At 11:30 a.m on August 13th 2016, in the construction site of Thai Binh 2 thermal power plant, LILAMA Corporation has conducted successfully pressure test (of Low Pressure Package) for Boiler 2 and finished pressure ...

Successful pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant

08:53 |27/07/2016

Vietnam Lilama Corporation constructor has successfully implemented a pressure test for boiler No1 of Thai Binh 2 Thermal Power Plant. The test results satisfy planed technical parameters.