coal combustion for the first time in unit n2 boiler of vinh tan 4 tpp

Coal combustion for the first time in Unit N#2 boiler of Vinh Tan 4 TPP

According to the information from GENCO 3, at 12:20 on June 27, 2017, coal burning for the first time at Unit#2 (600MW) of Vinh Tan 4 thermal power plant (TPP) was successfully implemented This is an important milestone as a basis for following testing steps with an aim to commercial operating Unit#2 at the end of 2017.