Unit 1 of the Mong Duong II BOT Thermal Power Plant (TPP) as been put into operation

Unit 1 of the Mong Duong  II BOT Thermal Power Plant (TPP) as been put into operation - 

Unit 1 of 1120 MW BOT Mong Duong 2 TPP has been put into operation


Inauguration ceremony of the Unit 1 of 1120 MW BOT Mong Duong 2 TPP.

On March 20, 2015, in Quang Ninh province, the General Department of Energy (GDE) in collaboration with the Electricity of Vietnam (EVN), Vietnam National Coal – Mineral Industries Holding Corporation (Vinacomin) and the Quang Ninh Provincial People's Committee (PPC), Corporations: AES (USA), POSCO Energy (South Korea), Chinese Investment General (CIC) and related entities held the ceremony for putting Unit 1 of the Mong Duong II BOT TPP into operation.

Speaking at the ceremony, Mr. Le Tuan Phong - Deputy General Director of GDE high appreciated the efforts of the Investors, BOT Company and Vietnam Doosan Company for completing the construction of and putting Unit 1 of Mong Duong II TPP into commercial operation in nearly a month ahead of time and with a good guarantee of labor safety.

Mong Duong II BOT TPP was started for construction in August 2011 in Cam Pha Town, Quang Ninh province. The TPP is developed by AES (51% equity), POSCO Energy (30%), CIC (19%) with BOT scheme, directly managed and operated by AES – TKV Power Ltd in 25 years before transferring to Vietnamese side.

As known that the overall progress of Mong Dương II TPP has been reached up to 99% with 85% checked and taken over progress.