On January 31, the unit #1 of the Duyen Hai 1 TPP (622.5MW) was successfully synchronized to the National Power System.

Duyen Hai 1 TPP is sited at Dan Thanh commune, Duyen Hai Dist, Tra Vinh province within Duyen Hai Power Center. The TPP consists of 2 units with a total capacity of 1,245 MW and power generation about 7.8 billion kWh per year.

Duyen Hai 1 project is a coal fired traditional steam condensate TPP. The plant has a modern combustion technology with the subcritical steam parameter; high availability, efficiency, stability and safety; and satisfies requirements of environmental protection due to applying methods of dust filtering, NOx and SOx deoxidizing by today modern and advanced equipment.

4308 MW Duyen Hai Thermal Power Center is invested by EVN Genco1, with an about $5 billion total investment.

Duyen Hai TP Center includes four units with the traditional steam condensate turbine technology and a largest in Mekong Delta coal port.